20-0326 v4.0 Applicability of Responsible Water Use Requirements to Interiors Typology

Question

Our project is an interior fitout delivered by a tenant within a building. The building is owned by a separate organisation. The tenant does not have the right to modify parts of the building not under its control.
In LBC v4.0 this credit is noted as 'scope dependent' for the Interiors typology but there is no clarification on how the requirements apply.
We propose that the stormwater requirements are not applicable to this project.

Answer

Given that this project falls under the Interior Typology, the I05 Responsible Water Use stormwater requirements are considered out of scope for this project. 